March 9, 2021 Item CCW 2021-075 ERRC
| The purpose of this item is to provide an update on the recent legal developments and the Local Planning Approvals Tribunal (LPAT) Process.
|
---|
October 13, 2020 Item CCW 2020-303 ERRC
| The purpose of this item is to provide an update on the status of the on-going land use approval process, and additional studies currently being undertaken and next steps.
|
---|
November 26, 2019
ERRC
|
The report provides an overview of the status of the
on-going land use approvals process and the outcome of the Case Management Conference (CMC) which was held on November 6, 2019 at the Township of Springwater Administration Centre.
|
---|
ERRC
|
The report provides an overview of the status of the
on-going land use approvals process, additional studies being undertaken and next steps.
|
---|
February 12, 2019
Item CCW 2019-052
ERRC |
The report provides an overview of the ERRC project, the status of the on-going land use approval process, and additional studies currently being undertaken and next steps. |
---|
February 12, 2019
Item CCW 2019-058
ERRC |
The report provides the background and details for the Notice of Appeal regarding County of Simcoe Official Plan Amendment No. 2. |
---|
September 26, 2017
ERRC
|
A Preliminary Business Case for the OPF and an updated Business Case for the MMF were presented to Committee of the Whole. |
---|
September 26, 2017
MMF
|
Updated Business Case for the MMF. This report provides an update to the 2014 financial analysis to consider development of the facility at 2976 Horseshoe Valley Road West, Springwater, and the impact of the Waste-Free Ontario Act on long-term transfer requirements. |
---|
September 26, 2017
OPF
|
Preliminary Business Case for the OPF undertaken by Ernst & Young. Their report assesses the business and operational impacts, associated risk, and cost/benefit of various options for organics management options. |
---|
June 13, 2017 Item CCW 17-174 ERRC
|
The report provides details on two recent pieces of legislation that could potentially impact project timelines for development – Growth Plan 2017 and Bill 151 – the Waste-Free Ontario Act. |
---|
February 10, 2017 | The Community Engagement Committee (CEC) met to discuss the status of the project – including the Request for Information for Organics Management Options, the Preliminary Business Case, and new committee members. |
---|
January 24, 2017 |
The report provides information regarding the Planning process and the OPF preliminary business case. |
---|
November 8, 2016 Item CCW 16-376 ERRC | A revised
Development Strategy timeline was presented in early November.
|
October 25, 2016 Item CCW 16-357 OPF
| Direction to advance procurement of the OPF via design/build/operate (DBO) delivery model.
|
September 13, 2016 Item CCW 16-301 ERRC | Update on the Planning application submission, a new Community Engagement Committee (CEC) representative, and updates to the FAQs. |
September 8, 2016 Neighbouring Landowner Meeting Notes ERRC | The County met with neighbouring landowners to discuss the proposed OPF project delivery method and procurement strategy, the approved development strategy timeline, and were provided an update on planning studies. |
September 6, 2016 Minutes of CEC meeting OPF | The Community Engagement Committee (CEC) met to discuss the upcoming consultation on the OPF project delivery method, review draft communication material, and to provide recommendations to the Project Team. |
August 9, 2016 Item CCW 16-266 OPF | Informational item presenting various ownership and financing models for the OPF. |
May 31, 2016 Minutes of CEC meeting OPF & MMF | The Community Engagement Committee (CEC) met to discuss the required planning approvals, debrief of the April 19th Public Information Sessions, and replacement of Municipal staff representative on the CEC Committee. |
May 24, 2016 Item CCW 16-165 OPF & MMF | Details on the Development Strategy for the co-located facility. |
May 24, 2016 Item CCW 16-191 OPF & MMF | Update on the engagement process undertaken to date. |
Spring 2016 Session Material OPF & MMF | On April 19, 2016, the County hosted two public information sessions at the Simcoe County Museum. |
March 23, 2016 Neighbouring Landowner Meeting Notes OPF & MMF
| The County met with neighbouring landowners to provide a project overview and next steps. |
March 8, 2016 Item CCW 16-054 OPF & MMF | Preferred site presented to County Council. Recommendation to co-locate both the OPF and MMF. |
March 7, 2016 Minutes of CEC Meeting
OPF & MMF | The Community Engagement Committee (CEC) met to discuss the upcoming Public Information Sessions, review draft communication material, and to provide recommendations to the Project Team. |
---|