September 26, 2017
ERRC

A Preliminary Business Case for the OPF and an updated Business Case for the MMF were presented to Committee of the Whole.

September 26, 2017
MMF
 
Updated Business Case for the MMF. This report provides an update to the 2014 financial analysis to consider development of the facility at 2976 Horseshoe Valley Road West, Springwater, and the impact of the Waste-Free Ontario Act on long-term transfer requirements.
September 26, 2017
Item CCW 17-222
OPF​

Preliminary Business Case for the OPF undertaken by Ernst & Young. Their report assesses the business and operational impacts, associated risk, and cost/benefit of various options for organics management options.​

June 13, 2017
Item CCW 17-174
ERRC

The report provides details on two recent pieces of legislation that could potentially impact project timelines for development – Growth Plan 2017 and Bill 151 – the Waste-Free Ontario Act.​

​February 10, 2017
​The Community Engagement Committee (CEC) met to discuss the status of the project – including the Request for Information for Organics Management Options, the Preliminary Business Case, and new committee members.
 
January 24, 2017
The report provides information regarding the Planning process and the OPF preliminary business case.​

November 8, 2016
Item CCW 16-376
ERRC

A revised Development Strategy timeline was presented in early November.

October 25, 2016
Item CCW 16-357
OPF

Direction to advance procurement of the OPF via design/build/operate (DBO) delivery model.

September 13, 2016
Item CCW 16-301
ERRC

Update on the Planning application submission, a new Community Engagement Committee (CEC) representative, and updates to the FAQs.

September 8, 2016
Neighbouring Landowner Meeting Notes
ERRC

The County met with neighbouring landowners to discuss the proposed OPF project delivery method and procurement strategy, the approved development strategy timeline, and were provided an update on planning studies.

September 6, 2016
Minutes of CEC meeting
OPF

The Community Engagement Committee (CEC) met to discuss the upcoming consultation on the OPF project delivery method, review draft communication material, and to provide recommendations to the Project Team.

August 9, 2016
Item CCW 16-266
OPF

Informational item presenting various ownership and financing models for the OPF.

May 31, 2016
Minutes of CEC meeting
OPF & MMF

The Community Engagement Committee (CEC) met to discuss the required planning approvals, debrief of the April 19th Public Information Sessions, and replacement of Municipal staff representative on the CEC Committee.

May 24, 2016
Item CCW 16-165
OPF & MMF

Details on the Development Strategy for the co-located facility.

May 24, 2016
Item CCW 16-191
OPF & MMF

Update on the engagement process undertaken to date.

Spring 2016
Session Material
OPF & MMF

On April 19, 2016, the County hosted two public information sessions at the Simcoe County Museum.

March 23, 2016
Neighbouring Landowner Meeting Notes
OPF & MMF

The County met with neighbouring landowners to provide a project overview and next steps.

March 8, 2016
Item CCW 16-054
OPF & MMF

Preferred site presented to County Council. Recommendation to co-locate both the OPF and MMF.

March 7, 2016      
Minutes of CEC MeetingOPF & MMF

The Community Engagement Committee (CEC) met to discuss the upcoming Public Information Sessions, review draft communication material, and to provide recommendations to the Project Team.